Guide · England · Planning
For homeowners planning an extension and self-builders applying for a single home in England. Two things changed this autumn. Since 31 October 2026, a planning officer decides householder and small residential applications. From 8 December 2026, planning fees go up.
Last updated 16 November 2026. Based on GOV.UK's national scheme of delegation guidance (published 1 June 2026) and SI 2026/1192 on legislation.gov.uk (made 10 November 2026). Check the details for your project with your council.
The Town and Country Planning (Discharge of Local Planning Authority Functions) (England) Regulations 2026 came into force on 31 October 2026. They set one national scheme for which applications planning officers decide and which can go to a planning committee. Schedule 1 lists the applications that must be delegated to officers. It includes:
Councils have to change their constitutions to match. The guidance says ward councillors can no longer call these cases in, and a set number of objections can no longer send a case to committee.
Source: GOV.UK — Planning committees and the national scheme of delegation: guidance for local planning authorities in England (MHCLG, published 1 June 2026).
A householder or minor residential application only reaches committee in a few cases:
For Schedule 2 applications, the presumption is still that officers decide. One can go to committee only if the nominated officer (normally the Chief Planning Officer) and the nominated member (normally the planning committee chair) both agree, and it raises an economic, social or environmental issue of significance to the local area, or a significant planning matter. If they can't agree, an officer decides.
Source: GOV.UK national scheme of delegation guidance (paragraphs 8–25).
The fees are set by the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) (Amendment and Transitional Provision) Regulations 2026. The draft was approved by both Houses of Parliament and made as SI 2026/1192 on 10 November 2026, so these are no longer draft figures. They come into force on 8 December 2026. The fees most relevant to extensions and small builds:
| Application | Fee from 8 Dec 2026 |
|---|---|
| Householder application: extension or alteration to one house | £575 |
| Householder application covering two or more houses | £1,130 |
| Works in the garden of a house (such as an outbuilding), or a gate, fence or wall on its boundary | £285 |
| Full application for new homes, fewer than 10 | £752 a home |
| Outline application for homes, site under 0.5 hectares | £719 per 0.1 ha (or part) |
| Permission in principle | £825 |
| Change of use to fewer than 10 homes | £700 a home |
| Confirming conditions are met: householder permission | £125 a request |
| Confirming conditions are met: other permissions, such as a new home | £435 a request |
| Non-material change: householder | £53 |
| Non-material change: other applications | £360 |
Prior approval applications for permitted development that had no fee before now cost £310.
Applications made before 8 December pay the fees in force before the change. The yearly fee increase then applies to the new amounts from 1 April 2027.
Sources: SI 2026/1192 as made and its new table of fees (legislation.gov.uk, made 10 November 2026); the approved draft regulations (legislation.gov.uk).
Work out which row applies with your designer or your council before you budget. If your extension to one house needs planning permission, the householder application is £575. A full application for one new self-build house is £752. Add a line for each conditions request you expect after approval. Each one is a separate fee.
You can add the planning fee as a cost line with its date in ConstructionPro.io. The app doesn't track planning applications or work out fees.
No. Since 31 October 2026, householder, minor commercial and minor residential applications must be decided by planning officers. GOV.UK's guidance says local practices such as ward councillors calling cases in, or a set number of objections triggering a committee, are no longer possible under the national scheme.
If the scheme is only homes, between one and nine of them, on a site smaller than 0.5 hectares, it is minor residential development under the Regulations and must be decided by an officer. If it is linked to a listed building consent application, or you apply for permission for work already carried out, it moves to the group that can go to committee by exception.
£575 for an application to enlarge, improve or alter one house, and £1,130 where it relates to two or more houses. Works in the garden of a house, or a gate, fence or wall on its boundary, cost £285. These are the amounts in SI 2026/1192, made on 10 November 2026.
From 8 December 2026, a full application to build fewer than 10 homes costs £752 for each home, so £752 for one self-build house. Applications made before 8 December pay the fees in force before the change.
Not any more. The draft regulations were approved by both Houses of Parliament and made as SI 2026/1192 on 10 November 2026. They come into force on 8 December 2026.
No. You can add the planning fee as a cost line with its date in ConstructionPro.io. The app doesn't track planning applications or work out fees.